Project Overview

Project Name: Jilin High-tech South District Makeshift Hospital
Location: Jilin, China
Construction Start: March 14
Site Leveling: Started on the afternoon of March 12 and completed after 36 hours
Installation Duration: 5 days for flat packed container house installation
Building Type: Flat Packed Container House / Modular Makeshift Hospital / Prefabricated Container House
Project Area: 430,000 m²
Isolation Rooms: 6,000 rooms after completion
Construction Mode: 24-hour uninterrupted construction
Usage: Makeshift hospital / COVID-19 isolation facility / Emergency public health response infrastructure

Project Background

The Jilin High-tech South District Makeshift Hospital was built as an emergency response project during the COVID-19 prevention and control period.

The construction site faced difficult weather conditions, including heavy snow. At the same time, dozens of construction vehicles operated continuously across the site to support ground preparation, material handling, and installation work.

On the afternoon of March 12, the construction team entered the site and began land leveling. After 36 hours of site preparation, the project moved into the flat packed container house installation stage. The installation work was completed within 5 days.

Construction Process

1. 36-Hour Site Leveling

Before modular installation, the construction team first carried out large-scale site leveling. This stage started on the afternoon of March 12 and was completed after 36 hours.

The fast completion of site preparation created the basic conditions for the following modular house installation work.

2. 5-Day Flat Packed Container House Installation

After site leveling, the project entered the modular installation stage.

Flat packed container houses were used as the main building units. The modular system allowed standard units to be transported to the site, positioned, assembled, and connected within a compressed schedule.

The installation was completed within 5 days.

3. 24-Hour Uninterrupted Construction

To meet the emergency construction schedule, more than 5,000 professionals of different types entered the site.

Construction was organized on a 24-hour basis, with personnel, vehicles, and equipment working continuously to support project progress.

4. Large-Scale Site Coordination

The project covered an area of 430,000 m², requiring coordination across ground leveling, material transportation, modular house installation, equipment scheduling, and on-site traffic flow.

Dozens of construction vehicles shuttled through the site during the construction period, supporting continuous operations in cold and snowy weather conditions.

Conclusion

The Jilin High-tech South District Makeshift Hospital was a large-scale emergency modular hospital project built with flat packed container houses.

After 36 hours of site leveling, the project completed modular house installation within 5 days. With a total area of 430,000 m² and 6,000 isolation rooms planned after completion, the project shows how prefabricated container house systems can be used for large-scale emergency isolation facilities under compressed construction schedules.

شارك هذه القصة، اختر المنصة التي تفضلها!

modular campIntegrated Modular Camp of Flat Pack Containers & KZ Prefab Houses for TJ03 Expressway
container house 2Container House Phase I of K1 Express Road | Modular Construction Camp Solution